Commission awards $3.14 million contract to renovate Fire Station 12 in Fairacres

3548732 · May 28, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Doña Ana County awarded a $3,136,351.38 contract to ESA Construction for renovations and additions at Fire Station 12 in Fairacres; facilities staff said bids were value-engineered to meet budget and the project faces a Doña Ana Mutual infrastructure cost.

Doña Ana County commissioners on May 27 awarded a construction contract not to exceed $3,136,351.38 to ESA Construction to perform renovations and additions to Fire Station 12 in Fairacres.

Justin Weaver of the county's Facilities and Services Department told the board bids originally exceeded available budgets. "When we went out to bid, bids came back at $3,450,000," Weaver said, and the county then "chose to value engineer the drawings" to bring the project within budget and accept the lowest responsive bidder at $3,136,351. Weaver said the project had been about six weeks behind schedule because of those procurement and budgeting steps.

Weaver also said Doña Ana Mutual — the local water utility — will require an approximately $500,000 infrastructure contribution for the site. He said facilities is using an interim construction strategy to proceed while working toward a longer-term agreement with the utility.

The commission approved the contract by motion and vote. Commissioners described the project as important to Fairacres, Picacho Hills and the county fairgrounds because Station 12 provides a wide coverage area for emergency response.

Why it matters: Upgrading Fire Station 12 advances county readiness for public safety and emergency response in a growing service area; the project includes construction, new site infrastructure and coordination with the local water utility.

What’s next: Facilities staff will proceed with construction under the awarded contract and coordinate with Doña Ana Mutual on required water infrastructure improvements. Weaver said some value-engineering decisions were required to keep the project within the available construction budget, and staff will return with implementation updates as the work proceeds.

Ending: The commission approved the contract and asked staff to keep the board apprised of the infrastructure agreement with Doña Ana Mutual and of construction progress.