Summary

The city approved Supplemental Contract No. 5 with Freese and Nichols for $145,000 to design pedestrian and culvert improvements related to the Chisholm Trail South project, including a new at-grade sidewalk across a creek.

Round Rock City Council approved a $145,000 supplemental engineering contract with Freese and Nichols Inc. to add design work for pedestrian improvements on the Chisholm Trail South Improvements O Town project.

Michael (staff member) told the council the supplemental contract will fund design of an at-grade sidewalk and extended culverts on the west side of the bridge to carry pedestrians across the creek. The work is intended to connect pedestrians from south to north and to allow the construction contractor (already awarded) to incorporate the improvements if schedules align.

"Our hope is that we can go in there and make some improvements to put the, extend the culverts on the west side at a surface, sidewalk," Michael said. He said the city will demobilize from the project at the November1 holiday period and remobilize in January to finish remaining work; if timing permits, the sidewalk piece will be added to the current contractor’s scope.