TxDOT briefs Mesquite on $540 million US 80/I‑635 reconstruction, completion targeted early 2029

3513178 · May 19, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

TxDOT told Mesquite officials the US 80 project will reconstruct the I‑635/US‑80 interchange, widen US‑80 and add frontage roads; construction began Feb. 2025 and the agency advises travelers to use DriveTexas.org for lane‑closure updates.

Nathan Petter, Dallas County area engineer for the Texas Department of Transportation (TxDOT), told Mesquite City Council members on May 20 that TxDOT has started reconstruction work on the US 80 corridor that includes a major interchange rebuild at I‑635 and US 80 and a widening of US 80 to three lanes in each direction.

"The project will improve mobility and bring the roadway to current design standards while meeting the needs of future travel demands," Petter said, describing the work as primarily an interchange reconstruction with additional widening and continuous frontage roads. He said construction began in February 2025, the contractor is Austin Bridge and Road, and the low bid for the project was "a little over $540,000,000." He estimated completion in early 2029.

The proj…

Already have an account? Log in

Subscribe to keep reading

Unlock the rest of this article — and every article on Citizen Portal.

  • Unlimited articles
  • AI-powered breakdowns of topics, speakers, decisions, and budgets
  • Instant alerts when your location has a new meeting
  • Follow topics and more locations
  • 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans