Farragut approves two change orders for town hall interior renovation; net contract rise remains just over $3 million
Summary
The board approved Change Order No. 2, adding $62,438 to the Wright Construction contract for town hall interior renovations, and Change Order No. 3, a credit of $21,876, leaving the contract just over $3 million.
Get email alerts on the Construction Contracts topic
No spam. Unsubscribe anytime.
The Farragut Board on May 22 approved two contract adjustments for the town hall interior renovation with Wright Construction, resolving previously identified change orders and credits.
Change Order No. 2 covers finalized costs for previously approved project change orders, including a reduced payment for the fire alarm upgrade; the net increase presented to the board was $62,438, bringing the contract to slightly more than $3 million. Change Order No. 3 records credits (including a sink credit and liquidated damages) and reduces the contract by $21,876.
A staff presentation summarized prior approvals and said the net change reflects PCOs that had already been authorized and a negotiated reduction in the alarm system cost. The board had previously approved an earlier change order in December for $11,219.
There were no public comments on the change orders at the meeting. Alderman White and Vice Mayor Meyer indicated no further discussion. The board approved the change orders by voice vote; the town recorded the approvals at approximately 6:22–6:23 p.m.
Staff indicated the contract, after these adjustments, remains just over $3,000,000. The board did not direct further action beyond approval of the changes.