Summary

Commissioners approved emergency purchases for a first-floor air-conditioning repair and a Parks Building shower installation and discussed the town procurement code’s emergency waiver and quote thresholds amid concerns about repeated single-vendor work.

The Town Commission on May 20 approved emergency purchases for a first-floor air-conditioning repair and for shower installation work at the Parks Building and discussed procurement procedures, vendor use and the town code’s emergency waiver provisions.

Director Morantos of the Public Services Department told the commission the First Floor compressor (or blower) had failed and staff authorized an emergency repair to avoid the risk of a second unit failing. “We did go ahead and… get that resolved,” Director Morantos said when presenting item 9.1. The director reported a cost in the record as stated: “$79.50. 8 thousand.”

Commissioners pressed staff to confirm whether components installed previously (during a prior maintenance period) were covered under warranty and asked for an update on a planned full replacement. Staff said a new cooling tower and other system modifications had been budgeted through ARPA funds and that a full retrofit had previously exceeded $1 million in an earlier RFP process.

Separately, staff sought retroactive approval for an emergency shower installation at Preserve Park so public-works employees could decontaminate after hazardous work. Commissioners questioned whether the work had been in place for years and whether the town’s procurement code had been followed; one commissioner noted seeing the same contractor (“Scott”) on multiple small projects and asked whether work was being split to stay under bid thresholds.

Town counsel explained the procurement code allows emergency procurement and waivers when an unexpected event threatens health, safety or town property and noted the commission itself decides whether a purchase qualifies as an emergency. Counsel also recited the town’s threshold: purchases above $5,000 and below $10,000 generally require two quotes absent an emergency waiver.

After discussion, motions to ratify the emergency purchases passed by roll call. The commission directed staff to check warranties and to return with documentation and recommended quotes or a procurement log showing how emergency determinations were made.

No exact, audited invoice amounts were introduced into the public record during the discussion beyond the staff-stated figures; where amounts were unclear in the transcript they are noted as reported rather than independently verified.