Council approves $109,610 change order for Veterans Park trail connection project

Brighton City Council on 2025-05-20 · May 20, 2025

Summary

City Council approved Change Order No. 2 with Hallmark Inc. for the Colorado Front Range Trail Veterans Park connection project, adding work required by CDOT and a realignment of a reinforced concrete pipe under a driveway.

Brighton City Council approved change order number 2 with Hallmark Inc., authorizing an additional $109,610 for the Colorado Front Range Trail Veterans Park connection project and authorizing the city manager or designee to execute the change order.

Ryan Smith, Parks Planning, Development and Grants Manager, told council that construction began April 14 and the extra cost reflects work required by the Colorado Department of Transportation (CDOT), including additional traffic control, curing and watering of concrete culverts, stormwater work and a decision to replace and realign an existing reinforced concrete pipe (RCP) under a driveway while the site is open.

Smith said the first change order (approved under city manager authority) covered the CDOT-required third-party inspector and totaled about $67,000. Change Order No. 2, for $109,610, covers the additional items and staff asked the council to also reset the city manager’s 10% change-order allowance. Smith said construction was nearing completion with about one month of work left.

Council Member Snyder asked whether the east side of the driveway connection to the pathway was included; Smith said the contractor is sequencing work to avoid disrupting the entire corridor and that the east side work would be included. Council Member Fiddler moved approval and Council Member Burpulowski (recorded as Berplowski in the minutes) seconded. The roll-call vote was 6-0 with two members absent.

AI generated

The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.

AI can make mistakes, so if you spot one, and we will fix it for everyone.

Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.

Source