Council awards $1.26M contract for Hoke at Ellington Memorial Library renovation

3442470 · May 19, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Town staff recommended and council approved a construction contract to renovate the 9,200-square-foot interior of the Hoke at Ellington Memorial Library after Vortex Construction submitted the lowest responsive bid at $1,259,030; construction expected June 2025–April 2026.

Christopher Gallant, capital program manager in the engineering department, recommended the Town of Clayton award a construction contract for the Hoke at Ellington Memorial Library renovation on May 20 after the town received four competitive bids.

Gallant said the project will demolish and renovate the entire 9,200-square-foot interior to modernize the layout for improved services and programming. He identified Vortex Construction Company as the apparent low bidder with a base bid and alternates totaling $1,259,030 and said that amount was well under the architect’s estimate.

Gallant told council construction is expected to begin in June 2025 with anticipated completion in April 2026 and that the architect of record and the town’s procurement contracts manager reviewed the bid package and recommended award to the lowest responsive bidder.

Council action

Staff asked the council to authorize the town manager or designee to execute the construction contract and any associated change orders needed to complete the project within the approved budget. The council then adopted Resolution 2025-40 authorizing the contract award.

Project context and community reaction

Council members who spoke during the item praised the project’s need and utility. Council Member Porter Casey and others noted regular heavy use of the library’s children’s area; several council members emphasized the renovation will improve sightlines and safety and praised the fact the low bid came in under the architect’s estimate.

Contract and schedule details

- Project: Hoke at Ellington Memorial Library interior renovation. - Size: approximately 9,200 square feet of interior renovation. - Apparent low bidder: Vortex Construction Company. - Apparent low bid (base + alternates): $1,259,030. - Bids received: 4 competitive bids. - Construction schedule (presented): begin June 2025, substantial completion anticipated April 2026.

The council adopted the resolution authorizing the town manager to execute the contract; the motion carried and staff said they will coordinate relocation of library contents and temporary operations during construction.