The county board reopened the consent agenda after discovering the low bid for a multi-use bike trail exceeded the grant award. After discussion the board approved awarding the contract to the apparent low bidder and directed the county engineer to eliminate or reduce contract items to lower county costs; the board also authorized using County
Get email alerts on the Bike Trail Bid Award topic
No spam. Unsubscribe anytime.
Beltrami County Commissioners reconsidered a consent-agenda award after staff disclosed that the low bid for a multi-use trail exceeded the anticipated grant amount. After discussion the board voted to award the contract to the apparent low bidder, directed the county engineer to trim scope items where feasible to reduce county costs, and authorized using County State Aid Highway (CSAH) funds to cover the remaining overage.
Why it matters: The bike-trail project had been advanced on the basis of a grant; bid openings later showed the lowest bid exceeded the grant award (the grant was stated as $710,000 and the low bid was $752,000, leaving roughly a $42,000 shortfall). Because the project is timed to construction while school is not in session, staff said awarding promptly is important to meet contractor schedules.
What staff told the board: Staff explained that early estimates were lower than the eventual bids and that construction-quantity detail changed during design. The engineer identified three options: (1) use county funds to cover the difference, (2) award and cut bid items to get closer to the grant, and (3) not award and cancel the project. The board discussed the options and requested staff pursue scope reductions where practicable. As recorded in the meeting, staff said the grant award was $710,000, the low bid $752,000 and that the project was therefore $42,000 over the grant amount.
Board action: Commissioner (mover) made a motion to award the contract to the apparent low bidder and to direct the county engineer to eliminate or decrease items to reduce county cost; Commissioner Wenger seconded. The motion specifically referenced using County State Aid funds where needed to cover the remaining difference if scope trimming did not fully close the gap. The motion carried on a 3–1 recorded vote.
Concerns and context: Commissioner Sumner said he had supported the project earlier on the understanding county funds would not be required; he objected to using County funds without more advance notice. Staff and other commissioners said that bid fluctuations are common and that grant-funded road and trail projects often require small local matches; staff noted a recent unexpected grant for a separate County 20 project that helped the highway program overall.
Next steps: The county engineer will proceed to execute the contract with the apparent low bidder, apply scope reductions as directed, and use County State Aid funds to cover the shortfall if necessary. Staff will provide commissioners with the detailed bid breakdown and the list of trimmed items.