Manager given 120 days to secure permits after multiple unpermitted alterations at 1012 Palm Beach Lakes Blvd.
Summary
City inspectors found fences, HVAC, electrical work and door/window replacements at 1012 Palm Beach Lakes Boulevard without the required permits. The special magistrate gave the property manager 120 days to obtain permits and complete inspections or face $50-per-day fines.
Get email alerts on the Unpermitted Construction topic
No spam. Unsubscribe anytime.
The special magistrate found multiple unpermitted alterations at 1012 Palm Beach Lakes Boulevard — including a new chain-link fence, air-conditioning equipment, electrical work and doors and windows — and ordered the respondent to obtain required permits and complete inspections within 120 days or face fines of up to $50 per day.
City inspectors told the hearing that stop-work notices and mailing/posting of violations occurred in February–April 2025, and that some permits were applied for but not yet issued. The case cites FBC 110.3 and FBC 105.1, the magistrate said when entering the ruling.
Kevin Pennington, a building inspector for the City of West Palm Beach, described his observations and the stop-work posting dated Feb. 12, 2025, and said the city recommends 120 days to comply and $50 per day after that. Joel Barrett, the property manager representing PBL Boulevard LLC, told the magistrate the fence permit had been completed and that HVAC and window/door permits were in progress. Barrett did not object to the city's recommendation for 120 days.
The magistrate accepted the city's evidence and found the property in violation of the cited Florida Building Code sections, ordering 120 days for compliance and warning of fines up to $50 daily thereafter. The magistrate also advised the respondent to stay in contact with the assigned code officer.