Board approves $42,000 change order to add lighting on First Street and River Drive

3420534 · May 21, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Board of Public Works approved a $42,000 change order to extend infrastructure for street lighting on First Street and River Drive; hardware (poles/fixtures) will be budgeted in 2026 and installation will follow separate procurement.

On May 20 the Board of Public Works approved Change Order No. 1 for the 2025 Street Construction Project B to add infrastructure for lighting along First Street and River Drive at a recommended cost of $42,000.

Staff said the addition was requested by a resident and supported by Alder Killian; staff reviewed the area and concluded the lighting “made sense” because a segment between River Drive and the rest of First Street lacked illumination. A staff member said the $42,000 is for infrastructure only; the poles and fixtures will be budgeted in 2026 and installed after that budgeting and procurement process.

Board member 1 moved to approve the change order; Board member 2 seconded the motion. The board voted in favor.

The approved change order adds conduit, wiring and related infrastructure to extend lighting through the identified gap; the meeting record does not show final vendor selections for poles or an installation schedule beyond the note that poles will be budgeted in 2026.