Needham panel approves large change order and $1.5M requisition for RTU replacements at Elliot and Broadmeadow
Summary
The Permanent Public Building Committee approved two change orders — a small $4,765.95 change order and a $693,455.76 change order — for the RTU replacement project and a CAM HVAC requisition for $1,500,138.00. Multiple designer and commissioning invoices were also approved.
Get email alerts on the Rtu Replacement Elliot Broadmeadow topic
No spam. Unsubscribe anytime.
The Permanent Public Building Committee on May 19 approved change orders and invoices for rooftop-unit replacement work at Elliot and Broadmeadow elementary schools, including a major change order related to roof work.
The committee approved change order No. 2 to CAM HVAC Construction for $4,765.95 and change order No. 3 for $693,455.76; both were funded from the general contractor’s budget and passed by roll-call vote. The committee also approved Requisition No. 1 from CAM HVAC Construction for $1,500,138.00 for services through April 11, 2025.
Why it matters: The larger change order covered additional roof replacement scope, including relocation of ductwork that was sitting on the roof deck and related work tied to the decision to replace full roof areas rather than repair limited sections. The committee was told the overall RTU project remains funded, and that a contingency remained in the project budget.
Details and contractor work: Ken, a project staff member, said the roof change order added ductwork relocation and that the project still had “a hair under a million dollars in the contingency.” He also reported a roughly $5,000 change for relocating an unmarked irrigation line encountered while excavating a pad and retaining wall at Broadmeadow; that work is complete.
The committee approved a group of contractor and consultant invoices tied to the RTU project: three invoices to GGD Consulting (total $10,825.00) for March services on Broadmeadow and Elliot and roof bid support; a commissioning invoice to NGNV5 for $828.45 for April services at Elliot; and the CAM requisition noted above.
Votes and procedure: Each motion was moved by the chair and seconded; roll-call votes were recorded for each item with the committee voting in favor. No member opposed the motions recorded in the meeting transcript.
Looking ahead: Staff said commissioning and final timing would continue as school schedules allow. The Broadmeadow unit was expected to be set in place shortly after school lets out and the team planned loam-and-seed follow-up work after the unit and fencing are in place.