Board awards $372,570 contract for Gardiner Bullis parking‑lot paving and ADA upgrades

AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Trustees approved a $372,570 contract with Tri Valley Excavating to complete ADA-compliant parking-lot work and pavement repairs at Gardiner Bullis, with work scheduled for July to avoid disrupting school activities and to meet Division of State Architect (DSA) requirements.

The board approved a $372,570 contract with Tri Valley Excavating Company to complete paving, ADA upgrades and associated repairs at the Gardiner Bullis school parking lot.

Why the work was needed: A prior shade-structure project funded by the PTA required DSA review; DSA review identified ADA upgrades to the parking lot and a subsequent civil-engineering review required changes to as-built conditions. The district rebid the resulting scope and added additional pavement repairs to improve efficiency.

Procurement details: After rebidding, the apparent low responsive bidder was Tri Valley Excavation. Staff said they held a post-bid interview, confirmed the contractor’s school-project experience, and scheduled the work for July so the district avoids disruption during active school days. The project must also receive final sign-off from the Division of State Architect (DSA), and staff estimated six to eight weeks for final DSA approval and certification after construction completion.

Board action: The motion to approve the contract was made by Vladimir and seconded by Stella and passed unanimously.

Questions from trustees: A trustee asked about asphalt color and heat-island concerns; staff said the surface will be standard asphalt and noted the new shade structure will provide shade to reduce heat. Trustees asked whether final DSA sign-off will come before school starts; staff said there is typically a short lag after construction for final paperwork but they planned to complete construction in July so the playground and parking-lot work should be functionally ready before school begins.

Ending: The board approved the contract and staff will coordinate timing with the school and DSA to minimize disruption.