Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Infrastructure topic

No spam. Unsubscribe anytime.

Council approves pay applications for MH 379 West reconstruction; contractor to begin paving in June

3413592 · May 21, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council approved two pay applications for the MH 379 West reconstruction project and heard a schedule update: subgrade work is complete, flexible base is being installed, paving is expected in June with substantial completion targeted for July and final completion in August.

The Mineral Wells City Council approved two pay applications related to the MH 379 West street reconstruction project and received a construction schedule update that puts paving in June and final completion in August.

Public Works staff reported that crews removed the existing pavement to subgrade, subcontractor BMS completed the cut, and contractor Peachtree Construction has been bringing in subgrade and flexible base. Staff said paving of the surface course is expected in June and will likely take three to four weeks to a month; the project remains on the previously communicated schedule with substantial completion expected in July and final completion in August.

Council approved Pay Application No. 1 (Peachtree Construction) by voice vote, and later approved Pay Application No. 2 for $270,233.67; both motions carried 7-0. During the update staff noted a roughly 100-foot alignment shift required additional paint striping handled via a work change directive; the estimated overrun for that change was described as about $500–$600.

Public Works staff offered to answer specific questions about pay applications and schedule but otherwise recommended approval to keep the project on schedule. Council confirmed there were no further questions before voting to approve the payment requests.

The approvals authorize payment to Peachtree Construction for completed work to date; staff will continue to monitor the schedule and change orders and report back in subsequent meetings.