LaSalle details nearly $9M in water and $3.8M in sewer projects tied to EPA loan-forgiveness

3411072 · May 20, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

City staff outlined a multi-year water and sewer capital program in the draft appropriations: roughly $9.94 million of water improvements and about $3.8 million in sewer projects are included in EPA loan requests; staff expect partial loan forgiveness and budgeted related one-time generator, SCADA and treatment upgrades.

City staff described large water and wastewater capital programs in the draft appropriations ordinance and said those projects are tied to EPA loan-and-forgiveness funding that remains under calculation.

"We are receiving quite a bit of infrastructure work for potentially 50% of the price," Finance Director John Duncan said when discussing the water fund, adding that water projects were expected to receive a higher forgiveness share than sewer projects.

Duncan and public works staff described $9,940,000 of water improvements in the EPA request; they said they expect roughly 50% forgiveness on the water portion and estimated 30–40% forgiveness on the sewer projects. The water fund line items in the draft include tower maintenance ($560,000, consistent with the city's tower maintenance agreement), a $200,000 generator plus a $50,000 transfer switch and SCADA upgrades, and $560,000 budgeted for other capital improvements tied to the EPA package.

On sewer projects, staff listed $3,800,000 in capital improvement projects and a maintenance-service budget of $1,500,000 that covers televising/cleaning (estimated $500,000), sewer lining (about $250,000), an aluminum lining ($50,000), an estimated $400,000 for the Route 6 pipe collapse, a wall-failure repair estimated at $100,000–$150,000, and a $130,000 gate replacement. Staff said a retaining-wall design by a structural engineer is nearly ready to bid.

Public works and utilities staff also discussed operational upgrades: two new water-tower generators, key-fob access for public-works buildings (budgeted at $30,000 under building maintenance), GIS locator equipment and new service bodies for vehicles (one service-body vehicle at $80,000), and a multi-year meter replacement program moving from Aclara meters to Neptune meters. Kevin Fay described the GIS gear as a field locator that will "pinpoint you within a couple inches of that valve lid" and said the meter-conversion program is roughly 60–70% complete and expected to continue another year.

Staff cautioned that the revenue side for loan forgiveness and some grant lines remain incomplete in the draft; final appropriation figures will be updated when the city receives the remaining EPA and grant accounting information.

Ending: The committee took no formal vote on these projects at the meeting; staff asked for direction and will update the final appropriation ordinance once loan-forgiveness and TIF revenue figures are complete.