East Canton water department: tanks to arrive May 26; staff will test pump-house communications
Summary
Public-works staff told councilors the village expects delivery of water tanks on May 26 and will run communication and fill tests between the pump house and power systems before work on the tower begins.
Get email alerts on the Water Infrastructure topic
No spam. Unsubscribe anytime.
Village public-works staff reported that water tanks for the village’s tower project are scheduled to arrive May 26 and that the department will test communications between the pump house and the power supply before proceeding with larger construction steps.
Staff said the tanks’ arrival date fell on a holiday (May 26 in the village’s reporting), and that crews would likely start work on the tower in July after the tanks arrive. The immediate plan is to fill the tanks, establish communications with the pump house and power systems, run the system for a few days to evaluate performance and then proceed to next steps.
The same presentation also noted smaller facility work underway at the police department (a new back-door lock and handle assembly expected in four to six weeks) and that zoning permits had been issued since the previous meeting.
No formal council action on the tower schedule was recorded; the item was given as an operational update and timeline.
Next steps: public-works staff will monitor the tank delivery, complete initial communication and filling tests, and update the council on progress.