County committee approves joint-development agreement for Muddy Creek Solar, moves it to full board

3355771 · May 16, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The executive committee approved a joint-development agreement for the Muddy Creek Solar LLC project and voted to forward the agreement to the full county board; project representatives attended the meeting in person and online to answer questions.

The Dunn County Executive Committee voted May 14 to approve a joint-development agreement with Muddy Creek Solar LLC and forward the agreement to the full county board for final action.

Supervisor Vogel moved to place the agreement on the county board agenda; Supervisor Steen seconded the motion, which passed on a voice vote. Committee members were told the agreement closely mirrors the county's prior agreement with the Elk Creek project.

Project representatives were present both in the meeting room and online. Alex Peterson, an attorney for Muddy Creek Solar LLC, introduced himself to the committee and offered to answer questions. "I'm not just some random person sitting on your screen, while I'm here," Peterson said, identifying himself as counsel for the project; he added that Mike Rosenow was in the room as the local project representative.

The committee did not amend the agreement during the session and recorded the motion in committee minutes; the agreement will appear on the county board docket for further consideration and possible approval.

No vote tally by name was recorded in the committee discussion portion of the transcript; committee members present voted by voice. The county will circulate the full agreement and related materials to board members ahead of the county board meeting.