Glide-slope contractor retainage unresolved; airport to contract DBT for final flight commissioning

3319863 · May 15, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The board discussed the TYQ glide-slope contract: a $109,000 payment to the prime contractor was released, but roughly $28,800 in retainage remains in escrow. Staff obtained a quote from DBT to perform final flight commissioning if needed and will work with legal to finalize paperwork to release retainage.

Airport staff reported progress on resolving final payments and commissioning for the TYQ glide-slope project but said retainage remains outstanding and will require legal paperwork before release.

Staff reported the authority released a $109,000 payment to the prime contractor, Harper, but about $28,800 in retainage remains in escrow. “We released that hundred and $9,000 payment...There’s still the retainage. It’s approximately $28,800,” staff said.

To complete final commissioning, the airport sought a direct proposal from DBT for flight commissioning work. Staff said DBT’s quote — about $16,000 — was higher than the credit previously negotiated with the prime contractor (approximately $11,987) but included additional support work the airport might need. Staff said the airport can contract directly with DBT to finish the flight check and commissioning.

Discussion: Staff and board members discussed next steps for clearing retainage and finalizing a change order that documents the agreed credit and scope changes. Staff said they will work with legal counsel and the escrow bank so the retainage can be released once documentation is in place; they do not expect to wait for the next board meeting if the legal steps can be completed sooner.

Direction: Airport staff will prepare the final change order and coordinate with legal and the bank to release retainage after appropriate signatures and documentation. The airport also has an agreed DBT quote on hand should the authority choose to have DBT perform the final flight commissioning.

Ending: Staff said the team will proceed with paperwork necessary to close Harper’s contract and arrange commissioning, and will update the board when the retainage is released or if additional approvals are required.