Board awards $487,388 sanitary rehab contract after staff flags urgent 30‑inch line repairs

3319221 · May 15, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Board awarded a $487,388 contract to Viseu Sewer Inc. for sanitary sewer rehabilitation after staff reported a deteriorated 30‑inch sewer near Avonshine Park that merits immediate lining to avoid repeated future digs and address significant deterioration.

The Board of Polyquarks and Capital Assets on May 13 voted to award the city’s 2025 sanitary rehabilitation project to Viseu Sewer Inc. for $487,388, and to amend the 2025 capital improvement budget to cover the larger-than-anticipated cost.

Staff described the project as part of a multi-year sewer-rehabilitation program. This year’s focus shifted to a segment around Avonshine Park after video inspections showed a 30‑inch main and manhole in much worse condition than previously captured. Staff recommended addressing the deteriorated 30‑inch main now so the work can be completed before a nearby subdivision connects and to avoid digging the same area twice.

Board members pressed on cost and bidding context. Staff said sewer rehabilitation costs have been high in recent years; more contractors are competing now as the market cools, but large-diameter work (30 inches) is expensive and exponentially more complex. Staff said existing reinforcement was exposed in the concrete main and that delaying work would risk further deterioration.

The board moved and approved awarding the contract to Viseu Sewer Inc. by roll call and amended the 2025 capital improvement budget as part of the approval. No specific construction start date was provided, though staff said they preferred to complete the work before the subdivision’s connections proceed.