Committee recommends $194,603.70 pay request for Jackson Community Center expansion
Summary
The Village of Jackson Budget and Finance Committee recommended the Village Board approve pay request No. 10 for the Jackson Community Center expansion in the amount of $194,603.70 and heard staff estimate one to two additional pay requests before project closeout.
Get email alerts on the Community Center Expansion topic
No spam. Unsubscribe anytime.
On May 13, 2025, the Village of Jackson Budget and Finance Committee recommended the Village Board approve pay request No. 10 for construction on the Jackson Community Center expansion in the amount of $194,603.70.
The pay request presented to the committee noted the amount of $194,603.70 and was recommended for approval by the Board of Public Works. A motion to recommend Village Board approval was made, seconded and carried by voice vote during the meeting.
A project staff member told the committee they had just received another change request and expected one additional change request after that, and estimated “1 or 2 more pay request[s]” would follow before the project is complete and closed out. The same speaker said the project is still expected to come in under budget when asked by a committee member.
The committee recorded the recommendation and will forward the pay request to the Village Board for final approval. Staff did not identify a firm schedule for final closeout at this meeting.