Council approves $152,843 change order for water tank and $110,635 pay estimate for Ogden water main
Loading...
Summary
Berwyn City Council approved Change Order No. 1 for additional repairs to the 4,000,000-gallon at-grade water tank ($152,842.75) and a pay estimate No. 2 for the Ogden Avenue water main replacement ($110,634.87) to be paid from ARPA funds.
The Berwyn City Council approved additional work and payments for two city water infrastructure projects: Change Order No. 1 for the 4,000,000-gallon at-grade water tank and pay estimate No. 2 for the Ogden Avenue water main replacement.
Public Works Director Robert Shiller presented Change Order No. 1 from Era Valdivia Contractors for additional repairs to the at-grade water tank in the amount of $152,842.75; the council concurred and approved the change order on a roll-call vote (7 ayes). Shiller described the work as not included in the original RFP and added the change order amount to cover the additional repairs.
The council also approved pay estimate No. 2 for the Ogden Avenue water main replacement project in the amount of $110,634.87 payable to the contractor (recorded as Bridal Construction in the motion), with the motion specifying payment from ARPA funds. That motion passed on a recorded roll-call vote (7 ayes).
Both approvals instruct finance and public works staff to process the payments and update project budgets accordingly; the motions on the record specified ARPA as the funding source for the Ogden Avenue payment.

