Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Building Safety topic
No spam. Unsubscribe anytime.
Nueces County estimates $10–11 million to retrofit courthouse with fire sprinklers; court to seek consultant
Summary
County staff reported an estimated $10–11 million construction cost to install a full sprinkler system in the Nueces County Courthouse under the 2021 International Fire Code; commissioners directed staff to prepare a compliance plan and bring consultant authorization back to the court.
Get email alerts on the Building Safety topic
No spam. Unsubscribe anytime.
Nueces County officials were told the county courthouse will require a full fire sprinkler retrofit that could cost about $10 million to $11 million, and the commissioners agreed staff should hire a consultant to prepare the plan the county must submit under the International Fire Code.
The update came during a public-works briefing to the Nueces County Commissioners Court, where a staff member reported the construction estimate and the legal timeline to comply: the county must submit a plan within 365 days of the city’s letter and will have up to 12 years to complete the required work.
The county’s assistant fire marshal, Tony Bettison, said the new requirement follows the county’s adoption of the 2021 International Fire Code and that several high-rise buildings in the city were being addressed under the same rule. “This is a life-safety issue,” Bettison said, adding that a fully sprinkled building is the “gold standard” of protection.
Commissioners and staff discussed what portions of the courthouse are already protected. Bettison and county staff clarified that the jail portion of the complex is already sprinkled because of its institutional occupancy, but much of the office space, including the commissioners’ courtroom, is not. Public-works staff said some header pipes exist at each floor and that fire alarms and evacuation procedures are in place now.
Officials flagged two consequential constraints that drove the retrofit requirement: building height and site layout. Bettison explained that a building floor that lies more than 20 feet above the lowest apparatus-reach point triggers the high-rise retrofit requirement; because the courthouse exceeds that reach when apparatus placement and site setbacks are considered, the code requires a full system rather than piecemeal alternatives.
Given the estimate’s size, commissioners asked about alternatives such as decommissioning upper floors or changing uses; staff said those options were not feasible because code triggers apply to the building shell and potential future uses. Public-works staff recommended hiring a consultant to prepare the plan the city must receive within 365 days and to assemble a phased construction schedule to control cost escalation.
Commissioners did not take a final procurement vote at the meeting. Instead the court directed staff to return with consultant procurement language and cost details; staff said they will add an item to the next meeting agenda to authorize hiring a consultant and to present a draft plan for submission to the fire marshal.

