Convention Center headquarters hotel: foundations in progress, vertical build expected in September; opening targeted for Nov. 2027

3312741 · May 15, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Project team reported auger-cast pile work and foundation construction underway, with vertical construction expected in September, a topping-out in July 2026, substantial completion in September 2027 and hotel opening in November 2027; committee asked for a July update on foundations.

City staff and the hotel project team told the committee that foundation work for the Miami Beach Convention Center headquarters hotel is underway and that the project is tracking toward previously announced milestones.

Project representatives said auger-cast piles and foundations are being installed and that a ceremonial groundbreaking is scheduled Friday. "We will be working on foundations until the August, and we will be able to see vertical construction in September," the presenter said, adding the team was tracking toward a building top-out in July 2026, substantial completion in September 2027 and an opening in November 2027.

Commissioner Laura Dominguez asked for the item to return in July to confirm whether foundation work was complete and whether the project remained on schedule for September vertical construction; staff agreed to return in July.

The committee did not take a formal vote; the committee recorded a direction to return the item in July to check schedule progress.