Atherton seeks more funding for Alameda de las Pulgas and El Camino safety projects; council weighs green-infrastructure trade-offs
Summary
Staff said the Alameda de las Pulgas traffic and safety project’s estimated construction cost is about $4 million and asked the council for a $1.15 million general-fund augmentation plus Measure W and A dollars. Councilors discussed shifting green-infrastructure allocations to cover part of the need and emphasized outreach and grant strategies.
Get email alerts on the Adlp Elcamino topic
No spam. Unsubscribe anytime.
Public Works Director Robert Avadio and Finance Director Robert Baron III presented the town’s capital-improvement program and asked the council for direction on prioritizing projects, timelines and funding for FY25–26 and a five-year outlook.
Why it matters: Alameda de las Pulgas (ADLP) and El Camino improvements combine safety, drainage and green-infrastructure requirements and are among the town’s largest pending capital projects. Their scope and funding affect multiple neighborhoods and influence grant-eligibility and match obligations.
Staff said the ADLP project’s construction estimate is about $4,000,000 and that the town already has roughly $2,000,000 available from prior budgets. To obligate design and construction dollars this year, staff requested augmentations including $400,000 of Measure W and $200,000 of Measure A transportation funds and a $1,150,000 general-fund request. Council members pressed staff to clarify the spreadsheet presentation and whether baseline green-infrastructure allocations could be moved into the ADLP budget to reduce the general-fund hit; staff said the green-infrastructure baseline could be reallocated toward ADLP if council so directed.
Council discussion focused on trade-offs (baseline green-infrastructure vs. targeted project funding), outreach and grant timing. Staff said they had recently received a 95% design submittal and need to complete cultural-resources and environmental work and obligate construction funds by September to remain eligible for certain state or regional funds. Council members suggested reducing the baseline green-infrastructure bucket and applying the difference to ADLP to reduce the general-fund requirement.
Staff also flagged that green-infrastructure set-asides are used to meet maintenance-of-effort and other grant requirements; council direction must consider those constraints. No formal appropriation occurred at the special meeting; staff sought policy direction so budget materials can reflect council priorities before final adoption.
Ending: staff will revise the CIP spreadsheet per council direction, show reallocations or grant-match strategies, and return with final FY25–26 budget materials for adoption.