Council authorizes bid for Ledge Road phase 2; project funded by Summit County permissive license tax

3248007 · May 9, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Macedonia City Council approved a resolution authorizing plans and bids to resurface the portion of Ledge Road between the railroad bridge and North Bedford Road. The work is funded entirely by Summit County permissive license tax funds and has an estimated cost of $225,000.

Macedonia City Council voted to authorize the city engineer to prepare plans, bids and specifications and to advertise for bids to resurface a portion of Ledge Road between the railroad bridge and North Bedford Road.

The action, approved as Resolution 32-2025, funds the second phase of Ledge Road paving entirely through Summit County permissive license tax funds, meaning the city’s general fund will not take a net hit. “This particular project is funded entirely through permissive license tax funds from Summit County,” Director Giladi said during the council meeting.

Council members discussed timing and scope. Director Giladi said the first phase of paving is scheduled to begin as soon as the week of May 19 and that the city hopes to begin the second phase immediately after the first is finished. Council and staff confirmed the paving will proceed “through the bridge and stop on just on the west side,” ensuring that paving will continue under the railroad bridge; “we're only paving. We're not widening the railroads,” Giladi added.

An estimated project cost of $225,000 was cited during the discussion. Council authorized three readings and then moved to adopt the resolution. A motion to pass Resolution 32-2025 was seconded and the council recorded the vote as “Aye” and the motion carried.

The resolution directs the city engineer to prepare bid documents and authorizes the mayor to advertise and solicit bids. No contract award was made at the meeting; council and staff said further administrative action will follow once bids are received.

Background: The work is described as Ledge Road paving phase 2, covering the segment between the railroad bridge and North Bedford Road. Phase 1 — the segment from North Bedford to Shepherd Road — was discussed as starting soon weather permitting. The council noted coordination with state and county paving schedules in the area.

Council members and staff emphasized schedule constraints tied to the construction season; staff said advancing the bidding process now would reduce delays and give the city the best chance to complete work this year.