IT cabinet sizing error delays LaSalle County data-center move; vendor to produce expansion pieces

3247590 · May 9, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

LaSalle County staff reported a manufacturing mismatch on new server cabinets: delivered racks are too shallow, creating a roughly 10‑week delay while the vendor builds expansion pieces. Staff said the county provided rack specifications but the delivered units do not fit current equipment, and crews are working around partial solutions.

LaSalle County staff told the property committee that a mismatch between ordered server cabinets and delivered cabinets has delayed the data‑center move and related floor work by roughly 10 weeks.

IT staff reported the new cabinets are "too small," explaining the existing equipment does not fit the delivered racks. A vendor representative from Rittal came onsite to assess options and proposed fabricating recessed expansion pieces to increase depth; staff said the minimum manufacturer order typically is for more expansion pieces than the county needs and they are pursuing a waiver to produce only the three required units.

The county expects the vendor’s expansion pieces to take about 10 weeks to manufacture and ship. Staff said some interim work (fire suppression, air conditioning, and cabling) can continue while waiting for the expansion parts, but until the racks have the required depth IT cannot complete all equipment moves; staff warned tight door clearances would cause airflow and heating issues if racks were filled without expansion.

Why this matters: The cabinets house servers and networking equipment that support county operations. The delivery and sizing problem pushes back completion of infrastructure work in the basement and may delay other related facilities tasks.

Next steps: The vendor will fabricate the expansion pieces; the county is pursuing a waiver to reduce minimum order quantities. Staff will continue staged work where possible and update the committee when parts arrive and new timelines are firm.