Board approves $66,512 change order for ninth-grade gym; district plans ROTC demo, JROTC move and Applied Creativity Center ribbon cutting
Summary
The Bixby Board of Education on May 8 approved a $66,512.41 potential change order for the ninth-grade gym to add north-side parking and handicap access and heard staff outline summer facility projects including an ROTC building demolition and relocation of JROTC into the former media center.
Get email alerts on the Facilities Construction topic
No spam. Unsubscribe anytime.
The Bixby Board of Education on May 8 approved a potential change order (PCO 3) of $66,512.41 to the ninth-grade gym project to add paved parking and handicap access on the north side of the new gym. A board member moved to approve the change order and the motion carried with recorded aye votes from Amanda, Pablo, Matt and the chair.
District facilities staff also briefed the board on a slate of summer projects and longer-term facility plans. Staff described an intended demolition of the existing ROTC building, which district staff said is older and cost-prohibitive to maintain, and relocating JROTC into the former media center space. The district intends to reuse and retrofit the media center for JROTC and other specialized training, and to convert the existing ROTC footprint into additional parking.
District staff provided budget and timing context: they estimated demolition and related costs could be "under $200,000" but cautioned that subsurface conditions and utility work could raise costs. Staff said roughly $500,000 in lease money remains available to offset some project costs, subject to required IRS accounting for lease proceeds.
Other summer projects described included: work on the ninth-grade gym (roof panels and framing in progress), repainting and cosmetic work on the stadium press box and Powerhouse building, expanding esports facilities into vacated cafeteria space, repainting and selective interior work in elementary buildings, new playground drainage, and a planned ribbon-cutting for phase one of the Bixby Applied Creativity Center (innovation hub) scheduled for June 4. Staff told the board they expect the ninth-grade gym to be ready for the season if work keeps pace (one board member asked about completion; staff answered “October, so let's count on November”).
Why it matters: the board's approval of the change order adjusts project contingency spending and affects the schedule for the ninth-grade gym. The ROTC demolition and building repurposing are intended to solve long-standing facility and parking constraints and to provide improved instructional space for JROTC and esports.
Board action and approvals: the PCO 3 change order for $66,512.41 was approved and paid from project contingency funds; staff said the price does not alter the guaranteed maximum price (GMP) of the larger project. The board did not approve a demolition contract at the May 8 meeting but discussed estimates and the need for further planning and bids; staff said they will return with bids and final budget figures.
Project risks and next steps: staff highlighted potential unknowns that could increase demolition costs (utility capping, lines under the building) and the need to coordinate with city permits and inspections. Staff said they will obtain bids for the ROTC demolition, firm up cost estimates, and present formal contract options for board approval in a future meeting.