County approves $656,069 engineering contract for Little Haines Creek bridge project
Summary
The Newton County Board authorized the chairman to execute a professional‑services agreement with Michael Baker International for Phase 1 engineering on the Little Haines Creek bridge replacement on Down Veil Road; the phase is budgeted at $656,068.95 and will require a future task order to complete construction plans.
Get email alerts on the Infrastructure Bridges topic
No spam. Unsubscribe anytime.
The Newton County Board of Commissioners approved a professional‑services agreement with Michael Baker International Inc. for Phase 1 engineering on the Little Haines Creek bridge replacement on Down Veil Road.
Public works director Chester Clegg told the board the existing bridge is load‑rated at 7 tons — adequate for a typical loaded pickup but insufficient for heavier vehicles — and replacement planning is under way. The county received seven responses to its RFQ and the selection committee chose Michael Baker International as the most qualified firm.
The board approved $656,068.95 to fund the first phase of engineering work, which staff said will take a couple of years to complete and would require a future Board approval for a task order to finish the project and procure construction services.
Why it matters: The bridge is in Commissioner District 3 and current load restrictions limit certain vehicle movements; replacing the bridge will address safety, weight limits and long‑term maintenance needs. The board approved the Phase 1 agreement unanimously.