Public works reports water-line work around the square, Fieldmaster upgrades and paving bid; dumpster and sidewalk issues noted
Summary
Public Works Director Jack Williams reported crews are working night shifts on downtown water-line repairs with an estimated 4–5 week timeline, recommended capital upgrade for Fieldmaster tank-monitoring system, announced a blanket paving bid release May 28, and described a long-standing dumpster issue and near-complete sidewalk project.
Public Works Director Jack Williams updated the Board of Mayor and Aldermen on multiple downtown infrastructure and operations items, including an ongoing water-line project around the square, equipment modernization needs, and a paving procurement.
Williams said crews began work around the square and encountered undocumented storm drains and other subsurface conditions; construction will proceed on night shifts with a current estimate of four to five weeks to finish that segment.…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat