North Penn advances $259 million high school renovation; board approves advertising bid package 2
Loading...
Summary
The North Penn School District board on May 6 approved a motion to advertise bid package 2 for the North Penn High School renovation project, advancing the second and largest construction phase of a four‑phase program with a total estimated cost of about $259 million.
The North Penn School District board on May 6 approved a motion to advertise bid package 2 for the North Penn High School renovation project, advancing the second and largest construction phase of a four‑phase program with a total estimated cost of about $259 million.
The superintendent, Dr. Bauer, recommended advertising bid package 2, saying the work “will include renovations and additions in pods A, B, C, D and E.” The board voted to proceed; no opposition was recorded.
Why it matters: the multi‑phase program is designed to keep the school fully operational during years of construction by creating temporary classrooms and sequenced swing space, while delivering major upgrades to science labs, the cafeteria/food court, auditorium, athletic spaces and building systems across the campus.
District project manager Mr. Lynch of CHA Solutions and architect David Schroeder of Schroeder Group Architects presented the plan and schedule. Lynch summarized the overall approach: “We now have 4 phases of the work for the high school renovation project.” He told the board that phase 1 (natatorium and K pod work) is under contract and was roughly $2 million under budget after bidding. Schroeder described design details and finishes, noting the project team’s frequent coordination: “All of this is the outcome of weekly meetings.”
Scope and phasing: Phase 1 (underway) covers the natatorium, K pod renovations, temporary classrooms and certain site utilities. Phase 2 (bid package 2) comprises additions and renovations to A, B, C, D and E pods — including a large A‑pod addition that creates swing space — and is the phase advertised at the May 6 meeting. The district also described a Phase 2a plan to build a new transportation building (using a cooperative procurement with Gordian and a contractor) so the old facility can be demolished while bus services continue. Phase 3 will cover pods F, J, H and G (auditorium, tech ed and athletic spaces) and Phase 4 will be a site restoration contract at project close.
Budget and contingencies: Presenters showed line‑item budgets for each phase. Lynch identified an $800,000 construction contingency remaining on phase 1 and described phase 2 as having a construction cost just over $100 million, design and phasing contingencies that together bring the phase‑2 estimated project cost to roughly $125 million. Phase 3’s estimated cost was presented at about $88.7 million. The combined program total shown to the board matched earlier district estimates near $259 million. The team said escalation was currently set near 4% per year for estimating purposes.
Permitting and schedule risks: The team said site work for phase 2 is contingent on receipt of the NPDES (National Pollutant Discharge Elimination System) permit; one comment letter had been returned and the project team had responded. Bids for phase 2 documents are planned for late July with a possible alternate bid date, and the district planned to ask the board to act on awards in August. The presenters warned that permit timing could shift site start dates into fall and that contingency balances would be tracked and reported to the board as construction progresses.
Construction logistics and program details: The design calls for no modular classrooms; temporary classrooms and an A‑pod addition will create the necessary swing space. The team described planned classroom technology procurement (an initial line item of $131,000 for classroom/educational technology) and said the district will outfit rooms with ViewSonic displays and ceiling power/data locations to allow technology upgrades later. On food service, the team said the cafeteria/kitchen replacement will require phased demolition and temporary serving arrangements (auxiliary gym and concession area warmers; some off‑site prep) and that a full kitchen replacement could run June–December in a single sequence.
Accessibility and program function: The presenters showed designs intended to improve universal access and circulation, add daylighting, reconfigure the dining area into a food‑court model, and consolidate science labs into consistent, modern teaching environments. The design team said some net classroom gains are expected (roughly eight to 10 classrooms net, plus about 16 classrooms added in the A‑pod addition), though exact counts will be finalized as work proceeds.
Procurement approach: For the transportation building (phase 2a) the district plans a cooperative purchasing route through Gordian to obtain quotes from a contractor already competitively sourced; the district will coordinate site preparation in the phase 2 contract while the cooperative contractor erects the preengineered building.
Board direction and next steps: The board authorized advertising bid package 2. Staff and the design team said they will return with bid results, contingency tracking and further information on phasing, technology specifics and site permitting. The team will also provide community updates through the district renovation website, livestreams and meetings.
Quote attribution rules: quotations in this article are taken from district staff and the project team at the May 6 work session.

