Kirkland sues, appeals King County’s Houghton transfer station siting and EIS
Summary
Kirkland officials said the city has launched parallel legal actions contesting King County’s selection of Alternative 1B at the Houghton site for the Northeast Recycling and Transfer Station.
Get email alerts on the Solid Waste Nerts topic
No spam. Unsubscribe anytime.
Kirkland officials said the city has launched parallel legal actions contesting King County’s selection of Alternative 1B at the Houghton site for the Northeast Recycling and Transfer Station.
City attorneys and solid-waste staff told the council they had filed a notice of administrative appeal on March 27 and a complaint in Snohomish County Superior Court on April 21 challenging the siting choice and the adequacy of the final environmental impact statement (EIS).
Why it matters: The city says the county’s choice to expand into more of the old landfill footprint (Alternative 1B) raises different and greater transportation, hazardous‑materials and mitigation questions than the other alternatives. That, Kirkland officials argue, required fuller analysis in the final EIS and better documentation of the siting decision. The outcome could force King County to re-do parts of the EIS or change mitigation commitments; it could also affect whether the facility, as proposed, can be permitted in Kirkland.
What city staff told the council Jenna McGinnis, the city’s solid-waste program lead, summarized the county’s process and the options evaluated in the EIS: two alternatives at Houghton and one at Woodinville. She said the final EIS was released March 10 and King County announced Alternative 1B—the option that digs further into the closed landfill—on March 21.
City Attorney Darcie Eilers explained the two legal paths Kirkland has opened. The administrative appeal is focused on the EIS itself; it will be heard by King County’s hearing examiner and could require County staff to redo analyses if the examiner finds deficiencies. Separately Kirkland filed a superior‑court action that challenges the siting decision as arbitrary and capricious under the applicable code and state law, while reserving its claims tied to the EIS.
Officials identified the city’s main concerns as: - Insufficient transportation analysis for the difference between Alternative 1A (replacement at the existing footprint) and 1B (construction adjacent while the existing facility remains open), especially impacts during simultaneous operation and construction and impacts at several intersections the city says were not adequately evaluated; - Inadequate hazardous‑materials analysis and mitigation given deeper excavation into an old landfill under Alternative 1B, including risk to nearby workers and residents, likely higher mitigation costs and possible construction delays; and - Procedural issues: several substantive comments submitted on the draft EIS were not addressed clearly in the final EIS, and King County issued addenda that the city says did not allow adequate time or transparency for review.
Process and next steps Eilers said the hearing‑examiner pre‑hearing conference is expected in late June, though schedule adjustments are possible; she also said the city has engaged outside counsel to support the administrative appeal and the superior‑court matter. The city expects the county’s hearing examiner may consolidate Kirkland’s appeal with a separate appeal filed by a citizen group (Phil Allen and Friends of Taylor Fields) to avoid inconsistent outcomes.
Kirkland staff also told the council that if King County later submits a permit application in Kirkland for construction, that local permitting process (a Type B permit) will include additional project‑specific review and public hearings; the council would be notified when a permit application is filed and council members would need to follow ex parte rules for hearings.
Council members asked how remedies might look. Eilers said a successful administrative appeal could require County staff to redo parts of the EIS; it would not by itself prevent King County from keeping the siting decision, but it would require fuller evaluation consistent with statute.
Where the city’s public information is posted Staff told the council they have compiled documents and links on the city’s web page kirklandlaw.gov/nerts and will continue to update the site as the appeals proceed.