North Penn board approves advertisement of bid package 2 for high school renovation
Summary
The North Penn School District Board of School Directors voted May 6 to advertise bid package 2 of the multi‑phase North Penn High School renovation, moving procurement forward for work in pods A–E while scheduling and permitting for later phases continue.
Get email alerts on the K12 School Construction topic
No spam. Unsubscribe anytime.
The North Penn School District Board of School Directors voted May 6 to advertise bid package 2 of the district's multi‑phase renovation of North Penn High School, moving procurement forward for work in pods A, B, C, D and E and related site work.
The board's action authorizes the district to solicit bids for the second major package of work after phase 1, which is already under contract and includes the natatorium and K pod renovations. The district's design and construction team told the board that phase 2 includes a new A‑pod addition to create swing space, multiple pod renovations, major site work and abatement, and an estimated construction cost just over $100,000,000 with a total estimated phase 2 project cost of just over $125,000,000.
Why it matters: the renovation is the largest capital project in the district's plan and is being delivered in four phases so that work can begin immediately on earlier components while later components are refined, bid and scheduled. The schedule for phase 2 and the transportation building is contingent on a National Pollutant Discharge Elimination System (NPDES) permit; designers said receipt of that permit could be as late as October and will determine site‑work start dates.
Project scope and phasing Mr. Lynch of CHA Solutions and David Schroeder of Schroeder Group Architects walked the board through the plan for four phases. Phase 1 (underway) covers the natatorium and K pod, including temporary classroom construction to create swing space. Phase 2 covers pods A–E (north of the auditorium) and includes the A‑pod addition, renovations to classroom clusters, library/media updates, new food‑service distribution and kitchen work, and substantial site work. Phase 3 will cover the remaining pods (F, J, H, G) including the auditorium and performance/music spaces; phase 4 is intended as a final site contract to restore pavement, landscaping and final stormwater work.
Budget and contingencies The presentation gave phased budgets rather than a single lump sum. Mr. Lynch highlighted the project reporting approach and recommended watching construction contingency as a primary indicator of project health; he pointed to the roughly $800,000 construction contingency remaining on phase 1. For phase 2 the design team showed a construction contingency in the range of about $11,000,000 and called out additional design and phasing contingencies (the presentation identified a combined figure in the millions; board members asked for and received explanations of those contingency categories). Lynch said, "To be clear, that is the district's money. And so whatever is left rolls to whatever phase or purpose you would like to use it for." The architects and construction team reiterated an overall project estimate consistent with previously shared totals (the team cited roughly $259 million for the entire multi‑phase program).
Permitting and schedule risks The team said the phase 2 schedule is driven by the district's receipt of an NPDES permit from the conservation district. Designers reported one comment letter has been returned and that the permit might not be issued until October, which would delay site work and shift downstream dates; bids are planned to be advertised this month with due dates in July and the board would be asked to act on awards in August if the schedule holds.
Transportation building and odd lot work The team described a separate but related component, phase 2A: replacement of the transportation facility. To accelerate delivery and maintain continuity of bus operations, the district will pursue a cooperative purchasing route (Gordian) for the building shell while phase 2 contractors complete the site work. The transportation building design includes bus bays, wash bay alternates, a mezzanine and storage, and will be sited north of the existing structure; move‑in into the new facility is planned before demolition and abatement of the old building.
Student experience, accessibility and systems Architects showed renderings and programming for classrooms, science labs, PACE and post‑12 labs, a consolidated dining/food‑court area, brighter daylighting through added windows, and wayfinding graphics. Several board members asked about accessibility; designers said revisions will increase universal accessibility (for example, ramped approaches and cutouts to allow wheelchair seating among peers) and that the scheme is intentionally more accessible than existing conditions.
Technology and food service logistics The team described educational technology plans and said the district will procure classroom AV and presentation systems (the presenters referenced ViewSonic displays currently in many rooms and said rooms will be wired to accept future technologies). On food service, district operations staff explained temporary arrangements: concession areas near the gyms will be converted into serving areas, some off‑site food prep and warmed deliveries are planned, and the goal is to continue serving warm meals while the main kitchen is demolished and rebuilt during construction.
Board action and next steps At the end of the presentation the board voted to advertise bid package 2; the motion passed (mover/second not specified in the public record segment). The projected next steps the team gave the board were: advertise documents this month, receive bids in late July (with an alternate date identified), award in August if the permit and review timeline permit, and begin site work after NPDES permit receipt. The team also said the district will keep the public informed via a renovation website, livestreams, newsletters and school district communications.
What the board approved elsewhere in the meeting The board also approved routine contract and personnel items, including summer hires for extended school care; the personnel motion passed with one recorded abstention on the summer hires because two recommended people were related to a board member (the transcript records an abstention but does not identify the abstaining member by name in that public segment). The board elected Joanna Chavez as board secretary and Tara B. G. Houser as board treasurer (motions passed).