Drainage board approves Best Way trash transfer station; staff notes tile reroute and on-site storage
Summary
The board approved construction for the Best Way trash transfer station, with staff and the developer agreeing to replace damaged tiles, protect Ivy Tech's private tiling and provide compensatory on-site depressional storage.
Get email alerts on the Best Way Trash Transfer Drainage topic
No spam. Unsubscribe anytime.
The Tippecanoe County Drainage Board approved construction for the Best Way trash transfer station after staff and the developer described measures to replace damaged drainage tile, protect private tiling on Ivy Tech property and provide equivalent on-site depressional storage.
Staff said that during rail spur construction some natural depressional storage was filled and that the developer plans to remove dirt to provide equivalent storage on-site so downstream flooding is not increased. Staff also said the developer will reroute and replace tile damaged by the spur and that the design ties into a structure at the southeast corner of the adjacent trailer park. Board staff noted Ivy Tech had installed an elaborate private tile system; the developer met with Ivy Tech and agreed to protect and repair that system as work proceeds.
A board member moved to approve construction per the Burke memo dated April 21; another seconded and the motion passed. Staff asked the developer to complete the tile reroute and detention basin work early in construction so those protections are in place before other building activity proceeds.
No public comment was made at the meeting on this agenda item.