Highway staff report progress on Golden Bridge replacement on Lexington‑Leroy Road

3225279 · May 8, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

County Highway staff reported that pile driving, pier caps and abutment work are complete and that deck forming and pouring are expected next week on the bridge replacement along Lexington‑Leroy Road; project photographs were shared with the committee.

County Highway Department staff provided a construction update on the Golden Bridge replacement project on Lexington‑Leroy Road, reporting progress on pile driving, pier encasement and abutment work and a near-term schedule for deck forming and pouring.

Staff showed photographs and explained that crews drove piles for the north pier, formed and poured pier caps and abutment caps, and placed riprap around abutments. The contractor had removed the south half of the old bridge to allow crane access, and staff said they expect a forming system to arrive onsite next week; once the deck forms are set, pouring the deck could take roughly two weeks.

“The project’s moving along good,” Highway Department staff said, and noted most of the earthwork is complete so the remainder of work should progress quickly after deck pours and backfilling. Staff also mentioned related preconstruction activity on other projects — a Route 66 bike trail segment and PJ Keller Highway work — as the department transitions into summer construction season.

No new actions were requested; the item was presented for information and committee members asked no follow‑up motions at the meeting.