Whitnall referendum update: schematic design ~ $78.55 million; Edgerton pool and addition scheduled first

AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

District staff and consultants gave the Board an update on design, schedule and budget for work funded by the Whitnall referendum, reporting a schematic design budget of about $78.55 million (roughly $550,000 under the referendum cap) and describing plans to build an Edgerton pool and classroom addition first, followed by high school renovations.

Whitnall School District board members received a detailed update on referendum-funded construction on Monday, including a schematic design budget of about $78.55 million — roughly $550,000 below the referendum authorization — and a timeline that puts construction procurement and a phased build beginning in 2026, district project staff said.

The update matters because the work covers multiple schools, involves a large portion of district capital funds and affects playgrounds, parking and daily operations during construction, project staff said. The presentation described site logistics meant to protect students during the school year and said the district will keep current pools and facilities usable until replacements are completed.

Project presenters from CG Schmidt and district staff summarized work now in design development, noted remaining schedule milestones and described how the referendum scope splits between major construction and soft costs. Ryan (project budget lead) said the schematic-design-level budget came in at approximately $78,550,000, which includes a $500,000 tariff contingency and is about $550,000 under the referendum total; the larger, published project total was shown at about $79.1 million, with roughly 80% of that amount identified as construction cost…

Already have an account? Log in

Subscribe to keep reading

Unlock the rest of this article — and every article on Citizen Portal.

  • Unlimited articles
  • AI-powered breakdowns of topics, speakers, decisions, and budgets
  • Instant alerts when your location has a new meeting
  • Follow topics and more locations
  • 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans