Salt Creek restroom nearing completion; LTAC ramp procurement faces tariff delays; staff flags RCO grant opportunities

3221421 · May 6, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Staff reported near-completion of the Salt Creek restroom repair under an RCO grant, said the Clallam Bay beach-access ramp LTAC project is delayed by procurement and tariff issues, outlined eligibility for multiple RCO grant programs, and noted regional road and parking projects that may shift visitation patterns.

Parks staff told the advisory board that the Salt Creek restroom repair funded by an RCO (Recreation and Conservation Office) grant is nearing final completion and that a remaining skylight and flashing issues remain to be fixed before the grant closeout this summer.

Why it matters: Capital grant projects advance infrastructure needs; delays or accelerations in park projects change visitor experience and affect county grant obligations and schedules.

Staff also reported procurement challenges on an LTAC-funded Clallam Bay park beach-access ramp. A vendor in fabrication experienced scheduling and pricing difficulties after tariff-driven material concerns and competition for fabrication slots; staff said the vendor and county are trying to meet a target installation for a July community event but noted there are no guarantees.

The parks director summarized available grant sources: the Washington State Recreation and Conservation Office has multiple programs and the county is eligible for roughly ten of them; other recurring grant sources exist for equipment, ADA improvements and facility stabilization. Staff said it is focusing on state grant cycles and will avoid most federal grants due to the additional reporting burden and limited staff bandwidth.

Staff also briefly shared regional infrastructure information from a recent meeting with county commissioners and Quileute tribal representatives: Morrow Road (access to Rialto) will be closed for reconstruction in 2026 and Upper Hole Road is scheduled to reopen with a late-spring ribbon-cutting; Second Beach parking and restroom capacity remain acute regional issues, with tribal partners noting large seasonal visitation and ongoing concerns about public waste and parking-safety configurations.

What's next: Staff will finish the Salt Creek restroom repairs and continue coordination with the Clallam Bay vendor; staff will also circulate a list of RCO grant programs and pursue grant opportunities where staff capacity and project readiness align.