Commission sets Sept. 30, 2025 completion date for AgCenter, approves EMS floor plan and directs contract steps
Summary
The Holmes County commission amended the AgCenter contract to set a Sept. 30, 2025 completion date, approved a floor plan for the new EMS building, authorized a construction‑management RFP, and directed staff to prepare termination documents for the EMS contractor as discussed in the meeting.
Get email alerts on the Capital Projects Agcenter Ems topic
No spam. Unsubscribe anytime.
The Holmes County Board of County Commissioners on Tuesday moved to set firm project timelines and next steps for the Government Efficiency Complex, approving an amended completion date for the AgCenter, approving an EMS building floor plan and authorizing procurement steps for construction management.
Commissioners voted to amend the contracting record so the AgCenter completion date is Sept. 30, 2025, an extension staff and the contractor requested after schedule delays. County staff said shop drawings and material deliveries delayed above‑ground work; contractor Trey (last name not stated) proposed the new date and recommended completion in late summer to early fall.
The board approved, by voice vote, an EMS building floor plan submitted in meeting materials and asked county staff to issue a limited‑scope request for proposals for construction‑management services to oversee the EMS project. County staff noted that ARPA and state grant deadlines constrain the project budget; the commissioners instructed staff and counsel to ensure procurement complies with grant and 2 CFR 200 rules.
During the meeting Sheriff Tate advocated using a metal building and county resources to reduce cost; he presented a vendor estimate for a metal building and said using county labor could reduce total cost and free funds for site work and furnishing. Commissioners discussed the tradeoffs between the originally planned stick‑built structure and a metal building; staff said the county would need a general‑contractor permit and that chosen approach must comply with engineering specifications and grant rules.
The board also authorized staff to prepare a termination document for the EMS portion of the Trey contract and to proceed with the new procurement steps; staff said the termination would not affect the AgCenter contract work. A separate discussion about whether to use stone or brick on the AgCenter façade was tabled so staff and the county engineer can confirm the contract/specification details and the engineer’s recommendations.