County signs change order for 5900 West bridge work; county share about 6.7% of roughly $6,485
Summary
A change order for additional work on the 5900 West bridge was presented; staff said the contractor did force‑account work to avoid extending a road closure and the total was about $6,485.16, of which the county’s cost-share is roughly 6.7%.
Get email alerts on the Capital Projects Change Order topic
No spam. Unsubscribe anytime.
County staff notified commissioners of change order number 3 for the 5900 West bridge project. Staff said an unplanned adjustment was required to reconstruct a wing wall at the southeast corner where a water line and irrigation turnout conflicted with the bridge work; the contractor completed the work on a force‑account basis to avoid extending the road closure.
Staff reported the change order totaled approximately $6,485.16, with labor comprising roughly half of that amount. Under the existing cost‑share arrangement the county’s portion was reported as about 6.7 percent. Commissioners reviewed the documentation, located the signature area, and the chair signed the change order so the contractor can be paid and the project can proceed.
Staff said the work was documented as a force‑account change order with recorded labor, materials and time; no additional contract scope beyond the adjustment was recorded in the meeting.