Blue Earth County awards $9.16 million Highway 10 reconstruction contract to R & E Enterprises

3218625 · May 7, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The county awarded a $9,158,881.02 contract to R & E Enterprises to reconstruct County State Highway 10 (including Bridge No. 90515) on a seven-mile rural section; the engineer’s estimate was about 2.12% lower than the low bid. Staff discussed staging and whether to delay the wearing-course overlay until after a winter freeze-thaw cycle.

Blue Earth County commissioners on May 6 awarded the contract for a seven-mile reconstruction of County State Highway 10 (including replacement of Bridge No. 90515) to R & E Enterprises of Mankato for $9,158,881.02, about 2.12% over the engineer’s estimate.

The project covers County State Highway 10 from the west county line to County State Highway 20 and includes rural reconstruction to meet higher design-speed curvature standards, full-depth reclamation in some segments and a bridge replacement. Staff told the board the project runs through a low-traffic rural corridor and recommended awarding to R & E based on their bid and previous county experience.

Nut graf: The project is one of the county’s larger reconstruction efforts this year and includes a bridge replacement; staff and commissioners discussed construction staging, including leaving a wearing-course bituminous overlay off for the first winter to allow settlement and then installing the top lift in a subsequent year.

Public-works staff said bidders advised the county to relax an earlier tight construction schedule; as a result, the contract was modified to allow the reconstructed sections to remain gravel through the first winter and receive a final wearing course later. Staff noted the tradeoff: shorter initial construction windows for bidders versus interim restrictions on vehicle loads and possible maintenance issues during the freeze-thaw season.

The board moved and approved award of the contract to R & E Enterprises. Staff will work with the contractor on final staging and a pavement schedule and said they may return to the board if budget or schedule modifications are needed to add the final wearing course in the same construction year.

Ending: County staff said they would monitor settlement over the coming winter and recommend whether to add the final overlay in 2026 or 2027 depending on budget and observed performance.