Board hears update on Big Bend Technical College construction: GMP near $4.4 million with identified savings
Summary
Dan, a district operations staff member, said the BBTC project fund stands at about $4.9 million, with architectural fees of about $450,000 and a construction GMP near $4.4 million; contingencies were listed at about $194,377.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
District staff and the project preconstruction team updated the board on the Big Bend Technical College (BBTC) construction project during the meeting, reporting the project budget, architect fees and the contractor’s gross maximum price.
Dan, a district operations staff member, told the board the project fund was about $4,900,000 and that roughly $450,000 of that would go to architectural fees. He said the project’s gross maximum price (GMP) was about $4.4 million and that the contingency in the current estimate was $194,377.
JT Ward, identified as the project’s construction manager on the preconstruction team, told the board the team had found several bidder savings during the estimating process. Ward said one electrical subcontractor the team expects to use bid about $300,000 lower than the figure currently plugged into the GMP, and the team expected additional adjustments as final bids arrived.
Board members asked about schedule. Ward said the team was advertising and targeting an optimistic construction start and completion timeline; he said they had been “advertising for January,” indicating a January target for occupancy if the timetable holds.
Ending: The board expressed appreciation for the precursory cost control work. Staff said they would return with final bid tallies, a final GMP for board consideration as needed and an updated schedule when procurement concludes.