County staff told commissioners the neighborhood grant totals roughly $9.2 million but bids for the combined park projects returned nearer $18 million; staff sought permission to accept the low bid to continue negotiations so the county can try to keep the work within the grant scope.
Get email alerts on the Parks Grant topic
No spam. Unsubscribe anytime.
County staff asked the board to accept the lowest bid for a state neighborhood grant covering improvements at Volunteer Park and Ambucks Park so negotiations could continue; staff said the county must accept a lowest bidder by the 90th day or rebid.
TJ (staff) said the original engineering and bid package was prepared by a consultant and produced an estimated project cost of about $9.2 million; when the work was put to bid later the bids came back substantially higher. TJ told the board the rebids returned a lowest bidder at about $18 million and staff has spent months negotiating reductions so the project can fit within the available grant funds.
TJ said, “we received around $9,000,000 and we are needing to keep the scope of the project as close as possible so that we can maintain the grant funds.” He also said the county needs to finalize terms and that accepting the lowest bidder is a step that preserves the county’s right to continue negotiations and, if negotiations fail, to rebid.
Why it matters: commissioners asked whether the grant was intended specifically for athletic-field work or for broader community spaces. Several commissioners said the apparent emphasis on baseball and football fields risked excluding other neighborhood uses (shade, walking paths, pathway lighting) and asked staff to provide the original grant documentation and legislative language that accompanied the funds.
Key numbers and constraints: staff said the original design work produced an estimated $9.2 million scope in 2023; receiving bids returned an $18 million price tag. The county must complete construction by late 2026 if it wants to secure certain federal/state funds, and staff said redesign and rebidding would add months to the timeline and risk losing the grant.
Commissioners directed staff to bring the grant documentation and a clearer breakdown of what the $9.2 million would buy at both parks, and to return at the 6 p.m. meeting with timeline and legislative text so the board could decide whether to accept the negotiated low-bid approach or rebid. No contract was awarded at the workshop.