Change order extends bridge-repair completion date by 42 days; daytime steel delivery scheduled
Summary
The Board approved change order No. 1 for a bridge-repair contract with Reith Riley that extends the substantial and final completion dates by 42 days and adjusts a steel-beam delivery time to allow daytime unloading, with no change in project cost.
The Board of Public Works and Safety approved change order No. 1 on May 7 for a recently awarded bridge-repair project with Reith Riley Construction Co., Inc.
Sergei Gertrzukin, Office of Corporation Counsel, explained the change order makes two administrative adjustments: it increases the date of substantial and final completion by 42 days and moves a steel-beam…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat