Wayne County committee hears update on emergency steel repairs to Grosse Ile Parkway bridge; work began May 1

3211877 · May 6, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

County staff told the Committee on Public Services that an emergency contract with CA Hull Co. began May 1 to make steel repairs to the Grosse Ile Parkway bridge; the bridge is closed during work, tolls remain in place, and township ownership means tolls are unlikely to be waived, officials said.

Steve Shea, Division Director of the Wayne County Roads Maintenance Division, told the Committee on Public Services that an emergency contract with CA Hull Co. is in place to perform steel repairs on the Grosse Ile Parkway bridge over the Trenton Channel. "The work has already commenced, started May 1 and [is] supposed to go... eight weeks," Shea said, adding the county hopes to finish sooner if weather permits.

The county said the bridge is closed for the repairs and traffic is being routed to the toll bridge. Commissioner Palamara noted prior closures and the recurring public request that the county cover tolls during county work. Palamara said the toll bridge was purchased by the township and "arguably, they could waive the tolls if they wanted to," but added she did not believe the township would suspend tolls because it used bond revenue to buy the bridge.

Commissioner Palamara asked whether the contractor had encountered unexpected conditions that could extend the schedule; Shea replied, "So far that I know of, everything is going, pretty good right now." County staff did not provide a detailed inspection report in the hearing.

The committee did not record a separate vote on the emergency procurement during the bridge update. At the meeting's close, a motion by Commissioner Palamara, supported by Commissioner Kinlock, to receive and file items 1 through 3 and approve items 1 and 5 was carried; the transcript records that motion as "carried" but does not list an item-specific roll-call for item 2. The transcript does not record a formal tally of individual votes for item 2.

Clarifying details provided in the meeting included that the bridge work began May 1 and that the county expected the contract duration to be up to eight weeks, weather permitting. The meeting record includes a discussion of local toll rates and traffic patterns during the closure but did not present an official county toll policy or any written agreement from Grosse Ile Township authorizing a toll waiver.