Summary

On April 3, 2025 the Concord Historical Commission approved Emerson Hospital’s request to demolish the on‑campus building known as the “White House,” conditioning approval on archival documentation, display of interpretive materials and reuse of select architectural features.

The Concord Historical Commission on April 3 approved Emerson Hospital’s request to demolish the on‑campus building known locally as the “White House,” with conditions requiring detailed historic documentation and public interpretation.

Hospital Chief Operating Officer Eric Stasney told the commission the relocated cottage—referred to on campus as the White House—no longer meets modern clinical standards and creates operational constraints the hospital cannot reasonably fix. “Heating, plumbing, electrical system are all outdated and poorly functioning,” Stasney said, adding that the building is not ADA compliant and multiple regulatory inspections “have recommended we should not offer any clinical services in this building.”

The commission’s condition requires Emerson to provide permanent documentation of the structure’s interior and exterior, deposit research and photographs with the town, and install interpretive materials in public areas of the hospital. Commissioner Lauren Meyer suggested the hospital pursue HABS‑level documentation and interpretive signage; Meyer said HABS (the Historic American Buildings Survey) Level I would be an appropriate standard for the record. Hospital staff agreed to consider relocating distinct architectural elements into the new emergency department and to work with the commission on interpretive plans.

Emerson representatives, including campus architect Chris Doohan and facilities director Robert Drake, described the hospital’s long‑term campus plan, which centers on an expanded emergency department. Stasney said the current emergency department is roughly 9,000 square feet and that seasonal patient surges and the closure of a nearby facility have driven a roughly 10% increase in ER visits; the planned expansion will add exam rooms, two trauma rooms and a behavioral‑health subunit. Stasney estimated the White House is roughly 15,000 square feet compared with the hospital’s overall footprint of a little more than 500,000 square feet.

Commission discussion emphasized preserving the building’s history in some form while allowing the hospital to proceed with urgent campus upgrades. Commissioner Nancy Frasselli Lee made the motion to approve demolition with the documentation and interpretive requirements; the commission voted to approve the motion. Melissa (surname not recorded on the meeting roll) was recused from the first item.

The commission did not direct the hospital to pursue any specific reuse plan beyond documentation and the selective preservation of architectural features; it left the technical and regulatory details — including fire‑code and health‑care regulatory limits on reuse — to hospital staff and building officials. The hospital said it will continue to consult with the commission about the documentation and interpretation plan.