Escambia County approves $19 million buyout and stormwater project for Windrose neighborhood

3211069 · April 17, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The board approved an acquisition and stormwater project tied to a flood-prone Windrose neighborhood. The project cost was stated at $19 million and staff said grant funding covers the match; the motion passed unanimously.

The Escambia County Board of County Commissioners on April 17 approved a county project to acquire properties and design/construct stormwater improvements tied to a flood-prone area (Windrose). The board voted 5-0 to move the item on the consent/budget agenda after a public speaker described leaving the neighborhood as part of the buyout process.

Dee Radel, who said she's participating in the county's buyout program through the group Flood Defenders, addressed the commission and described the mixed feeling of relief and loss when leaving a home because of repeated flooding. "We're getting out of a flood situation, but I'm leaving Escambia County, which is sad," Radel said, and she thanked county staff and volunteers who worked on the buyout process.

During follow-up questions on project cost and funding, a staff member identified as Joy (staff member) said the "total cost of acquisition, design, and construction" for the project is $19,000,000. Joy also advised commissioners that the project match is covered by grant funds and that no county general fund or local funds would be required for the match. Commissioners moved and seconded the consent/budget item and the motion passed 5-0.

Commissioners and staff briefly noted the long process of buyout and mitigation work and thanked residents and staff involved. The board also commended the community advocates who had assisted residents through the process.

What's next: With the consent action passed, staff will proceed under the grant terms to complete acquisition and move forward with design and construction steps described in the project backup materials.