Council approves extra $100,000 to complete Lampson Road sidewalk work to Martin Avenue

3207920 · May 5, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council added $100,000 to the contingency for the Lampson Road/Maple/Lincoln sidewalk reconstruction contract so the contractor can rebuild the sidewalk from New Meadow Road to Martin Avenue rather than a piecemeal approach; council also heard resident testimony about schoolchildren biking and walking on the route.

The Town Council approved an additional $100,000 to the construction contingency for the Maple/Lincoln sidewalk reconstruction contract, enabling contractor D'Ambra to reconstruct the Lampson Road sidewalk through to Martin Avenue in a single contract rather than in phases.

Why it matters: The project covers about 1,650 feet of sidewalk on Lampson Road, a route used by students traveling to Barrington schools. Residents told the council that children bike on the street and that motorists travel at high speeds; supporters said a contiguous sidewalk will improve safety and connectivity.

Town Manager Hervey said field work and a contractor's unit pricing allowed staff to expand the scope and finish the entire stretch under the existing contract rather than returning for a separate contract later. Staff warned that some trees with root damage will need removal to create a safe, level sidewalk; the town will consult the Conservation Commission and will seek to save trees where possible.

Resident Joe Palazzolo, who lives on Lampson Road, told the council he regularly sees children biking to school and said the lack of sidewalks creates a safety hazard. Council approved the $100,000 contingency increase by unanimous vote.

Ending: The contract change is intended to deliver a finished sidewalk from New Meadow Road to Martin Avenue in one mobilization; staff said they will pursue eligible state grants and return to the council with construction timing.