Board awards McCall Road North reclamation contract to Platinum Paving; 90‑day completion planned

3205041 · May 7, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The county awarded the McCall Road North full‑depth reclamation contract to Platinum Paving & Concrete LLC; project includes two‑week full closure during summer and roadway widening to 12‑foot lanes with 2‑foot paved shoulders.

The Effingham County Board on May 6 awarded the McCall Road North reclamation contract to Platinum Paving & Concrete LLC, county staff said.

Procurement and contracts staff reported Platinum was the lowest responsive, responsible bidder for full‑depth reclamation and asphalt overlay on a roughly 1.9‑mile corridor. The contractor submitted required documentation and the contract anticipates a 90‑day completion window from the notice to proceed. County engineering said the scope includes a two‑week full closure of the road segment between Ralph Ron and the Springfield city limits; traffic will be detoured via Little McCall and Braun Station during that short closure period.

County engineers explained the work addresses sections that previously had thin asphalt over clay subgrade; the reclamation and overlay will rebuild the section to a collector‑road standard, including widening to 12‑foot lanes with 2‑foot paved shoulders as part of the freight‑route network standard the county is implementing.

The board voted to award the contract; staff noted some related resurfacing and collector standards changes (mix types and shuttle‑buggy use) have been adopted for future projects to improve pavement longevity.

Next steps: a notice to proceed will be issued once contract paperwork is complete and scheduling for the planned two‑week closure will be coordinated with emergency services and public notifications.