Commission authorizes pursuit of easement so city can maintain water main at new health department site
Summary
The board agreed to pursue a 20-foot perimeter easement that would allow the City to own and maintain the water main loop serving the county's new health department facility, reducing the county's ongoing pipeline maintenance burden but exposing the county to some potential repair responsibilities.
Get email alerts on the Facilities Utilities topic
No spam. Unsubscribe anytime.
Liberty County commissioners authorized staff to pursue a 20-foot easement around the county's new health department site so the City can accept and maintain a public water main loop that will serve the facility.
County staff described the situation: the current construction ties into the city's system and the original design placed the county's water meter and backflow preventer at the site, which would have made those facilities county-maintained. The city's engineer suggested that if the county grants an easement for the perimeter loop of the water main the city would accept ownership and maintenance of that line, allowing the county to retain the meter and backflow as private facilities on its property. County staff said this approach would reduce the county's operational obligations but that the county could be responsible for paving repairs if the city has to trench for maintenance.
County Engineer Trent said that if the county did not grant the easement the county would need to relocate the meter and backflow to the public right-of-way, which he estimated could add roughly $50,000 to $60,000 in additional design and construction costs (staff estimate). Commissioners discussed the tradeoffs and asked staff to consult the city manager and the city council.
The board voted to authorize staff to pursue the 20-foot easement and directed staff to coordinate with the city for formal acceptance by the city manager/city council; the board noted the county would remain the property owner and would not cede site control.
Next steps: County staff will approach the city manager and the city council to seek formal acceptance of the easement arrangement and will return with any contractual terms or costs if the city requires additional work.