County reports post‑dredge survey results moving forward; Wake boat landing discussions continue with state
Summary
County staff reported a dredging project that should be completed with survey depths of about 8.5–9.5 feet at some locations; supervisors also discussed Wake boat landing funding and potential roadway/wall work to support periodic contractor dredging and public access.
Get email alerts on the Marina And Waterways topic
No spam. Unsubscribe anytime.
County staff told supervisors a dredging project is expected to finish this week and that early post‑dredge survey data show depths in some locations approaching 8.5 to 9.5 feet, exceeding initial estimates in places. A final post‑dredge survey is expected Thursday or Friday for confirmation.
Separately, supervisors discussed Wake boat landing, a long‑standing local access site. Staff said the county has notified state officials of interest and planned a meeting with state representatives. The board heard that state and local stakeholders are interested in constructing a short roadway and revetment/wall to facilitate contractor access for periodic dredging and provide public fishing access; supervisors encouraged stakeholder meetings including local contractors and the project’s citizen representative to develop a implementable plan.
Why it matters: Dredging depth affects navigation access and local boating/economic activity; the Wake boat landing proposal includes potential state funding and local contractor involvement for ongoing maintenance, which could reduce recurring state dredging demands.
Next steps: County staff will post the final dredge survey when available and continue coordination with state and local stakeholders on Wake boat landing options.