Residents press county on rough local roads as VDOT outlines paving and turn‑lane projects
Summary
A resident urged action on badly deteriorated roads during public comment; VDOT reported paving work across Deltaville-area routes and previewed an intersection left‑turn lane and bridge projects, saying a Route 333/Regent left‑turn addition could start December 2026.
Get email alerts on the Transportation topic
No spam. Unsubscribe anytime.
A resident urged Middlesex County supervisors to address several local roads he said are unsafe for school buses, while a Virginia Department of Transportation (VDOT) representative reported a slate of resurfacing and intersection improvement projects.
Resident Lewis Bridal told the board several roads (he cited numbers 1668, 2619 and 629) need “a total facelift,” describing deep cracks, standing water after rain and informal dumping that could threaten creeks during storms.
Why it matters: Local road conditions affect school bus routes, emergency access and drainage. VDOT staff confirmed some of the roads mentioned are already scheduled for resurfacing or routine maintenance; the board asked staff for follow-up and routing of concerns to VDOT.
VDOT update: Lee McKnight (VDOT) told the board the county is in paving season with work on Philpott Road, Route 620, Route 640, Stormont and Fishing Bay Road among routes receiving surface treatment. McKnight highlighted a proposed left‑turn lane onto Regent Road from Route 33 at the Route 333/626 Regent Road intersection, currently scheduled to begin December 2026, and a northbound bridge replacement over Dragon Run on Route 17 projected for early 2026 that could be accelerated. He also noted an upcoming public meeting for a shared‑use path segment on June 5.
Board response and follow-up: Supervisors asked staff to coordinate with VDOT on specific shoulder and ditch work for the roads raised during public comment and to pursue tree trimming in areas where vegetation narrows travel lanes. The chairman asked staff to email VDOT about a small paved section behind the middle school so crews can schedule work and to notify the county at least a week before crews begin so speed bumps can be removed.
Action items: County staff confirmed that the numbered roads the speaker cited had been added to future resurfacing and routine maintenance schedules; supervisors sought a follow-up report and photographs from the resident at a future meeting.