Summary

Facing uncertain state REDI disbursements, Decatur County commissioners approved continued construction draws, a rezoning/survey for the new community building parcel, a $3,000 surveyor contract, and a $2,000 fundraising video deposit; they also approved pay app(s) and a plan to use county funds if needed and seek reimbursement later.

Decatur County commissioners on May 5 voted to continue construction on the county’s Fairgrounds REDI project despite uncertainty about state fund disbursement, authorized a parcel rezoning and hired the county surveyor for $3,000, and approved a $1,000 upfront payment (50% of $2,000) for a fundraising video to aid private fundraising.

Commissioners described the REDI‑funded project as a roughly $4,000,000 effort: the board reported $1,950,000 expected from REDI, roughly $1.2 million committed from the county and about $800,000 from private donations and in‑kind work as written into the proposal. County officials said the state’s timing for releasing REDI payments is uncertain — estimates discussed at the meeting ranged from summer to January 2026 — and that other counties and projects are also awaiting disbursements.

County staff presented three options: halt work until state funds arrive; continue only to an "appreciable" point such as enclosing the building to protect materials; or proceed with the project and cover short‑term cash needs with county funds and then reimburse the county from REDI disbursements or a short‑term loan. Commissioners approved continuing the project and directed staff to pursue short‑term financing options if necessary while using available EDIT funds for immediate draws.

Commissioners also approved rezoning a 2.55‑acre parcel at the fairgrounds from agricultural (A) to a B3 classification to accommodate the community building and related setbacks. They approved a $3,000 contract with the county surveyor, Andy Schulley, to prepare the parcel survey needed for rezoning.

The board approved a pay application for the YMCA OCCA (state) grant that will flow through county administration: pay application No. 4 for the YMCA was $81,375.54 with a reported remaining balance/retainage of $576,627.93; commissioners voted to approve that draw.

The board also approved a $2,000 fundraising video contract from videographer Daniel Fademick, with a 50% deposit of $1,000 to be paid from EDIT funds; the video is intended to provide a single, consistent presentation for the fundraising committee and online outreach. Commissioners said the video and printed pledge materials will standardize outreach by roughly 20 members of the volunteer fundraising team.

Ending: The board said it will meet with REDI administrators and local council members to press for clarity on disbursement timing and will hold a readiness meeting Wednesday to discuss financing strategies.